Time value, rates and linear products
A project costs $100 today and pays $60 at the end of each of the next two years.
FoundationNumeric answer
A project costs $100 today and pays $60 at the end of each of the next two years. At an 8% discount rate, what is its net present value, to two decimal places?
Answer with a number. Fractions, powers and expressions like 23/6 or C(52,5) are read correctly in practice.
The worked solution is in Premium
The answer, the full working and the one idea to take away – for this and all 1,322 questions in the bank. Answer it in practice and your working is marked, with a known mistake named when you make one.
Report an issue with this question
Learn the method
More time value, rates and linear products questions
- What is the present value of $1,000 a year for ten years, first payment in one year, at 5%?Applied · Premium
- A project costs $100 today and returns $60 at the end of each of the next two years.Applied · Premium
- A project’s cash flows go negative, positive, then negative again (for example…Applied · Premium
- At 8% a year compounded annually, roughly how many years does money take to double?Foundation · Premium
- A loan charges 12% a year compounded monthly.Foundation · Premium
- A cash flow of $5 arrives in one year and then grows at 3% a year forever.Foundation · Premium